"The city must finish the altered part and then reapply for the original grant to complete the trail." That line comes from the minutes of the Eldon Board of Aldermen's May 26, 2026 meeting, where Mayor Vernon explained why the trail is coming together the way it is.
Eldon's first piece of the Rock Island Trail is a quarter mile of compacted rock, laid by the city's own street crew. The pace has depended on whatever equipment the crew could borrow or rent. That outcome was chosen. In August 2025 the city turned down a $250,000 federal grant to keep control of where the trail goes and what it's made of. Everything since, from the broken roller to the fence finished in late summer, follows from that decision.
The rule behind the $250,000 decision
On Tuesday, Aug. 12, 2025, the Eldon City Council surprised many people by declining a $250,000 grant for the Rock Island Trail. The money looked like a gift, but its conditions caused trouble.
City Administrator Mandy Asbury told The Advertiser what she had learned in a meeting with the Federal Highway Administration and Missouri State Parks. Federal Highway Administration grants require the trail to follow the rail line's exact path, in case a railroad ever has to be put back into service. On Eldon's stretch, that path would have sent the trail through a local business's parking lot. State Parks, which legally owns the corridor, still supported the trail. The federal rules, though, left no room to change the plans.
Turning down the grant changed more than the route. As The Advertiser reported, without the federal money the city didn't have to build the trail in concrete, which kept its costs down. So Eldon gave up a six-figure grant in exchange for two freedoms: moving the alignment away from a private business and using a cheaper surface. Asbury said the city was still committed to the trail and expected part of it to be finished by the end of that October.
Two weeks after the vote, on Wednesday, Aug. 27, 2025, city and state officials met to discuss building a short segment. The Advertiser's headline on that story described the route as running from Mill to the Eldon Drive-In. The October 2025 target still came and went, and work didn't start until the following spring.
What a city-crew build looks like
Construction started in spring 2026. On May 14, The Advertiser reported that City of Eldon Public Works employees were laying and compacting two-inch base rock and surface rock on the first leg. The aldermen's minutes, where Public Works Director Steve Johnson gives his updates, fill in the rest of the season:
- May 12, 2026: The street department had laid gravel up to the spot planned for a crosswalk. Weather permitting, the fence would go up the next week and the crosswalk would be finished.
- May 26, 2026: The roller the crew was using broke down. It had been borrowed from a contractor and had to go back. Renting one costs $400 a day. The last quotes for buying one ran $61,000 to $64,000. The board voted unanimously for a two-week rental.
- June 29, 2026: Trail work was set to resume after the Fourth of July.
- Aug. 25, 2026: The streets department had finished the main portion of the trail fence.
The roller decision shows the trade-off clearly. Buying a machine that costs more than $60,000 to finish a quarter mile would wipe out much of what the city saved by skipping concrete. Renting at $400 a day keeps costs down, but the work has to fit into rental windows and around the crew's other jobs. Those jobs are real. The same Aug. 25 report also covered a pool pump repair, cemetery fencing, a sidewalk project and a water main project. Alderman Walker asked whether a roller was among the equipment in a vehicle grant the city was applying for, and Johnson confirmed that it was.
A self-built trail moves at the speed of the department building it. That department also maintains the town's streets, water and sewer, and the pool.
The neighbors took the federal terms
Other towns along the old Rock Island line accepted federal money and its conditions. The Missouri State Parks community development page shows the difference:
| Community | Trail length | Federal grant | Local match | Status per State Parks |
|---|---|---|---|---|
| Versailles | 2 miles | $440,861.62 | $149,563.96 | On track for completion by Oct. 2026 |
| Belle | 1.67 miles, plus trailhead kiosk and water | $202,000 | $48,000 | Groundbreaking May 31, 2025; on track for Oct. 2026 |
| Owensville | 2.5 miles | $510,000 | $80,000 | Open; ribbon cutting May 31, 2025 |
| Gasconade County | 2.8 miles | $467,972 | $116,993 | Ribbon cutting May 30, 2026 |
| Eldon | 0.25 mile | None listed | None listed | "To be built"; future plans depend on grants |
Versailles is the closest comparison. It broke ground on its roughly two-mile city project on Oct. 17, 2025, the same day Cole Camp broke ground on a 1.77-mile segment with a trailhead. The Friends of Rock Island Trail's June 2026 progress report listed openings in Gerald, Owensville and Gasconade County and described Eldon as beginning a similar local effort.
The table is easy to misread as other towns getting ahead while Eldon fell behind. The federal requirement to keep the exact rail alignment applies everywhere. It only became a deal-breaker where that alignment ran into something like a working business's parking lot. Eldon hit that problem, and Versailles and Belle apparently did not.
The quarter mile comes first
The mayor's May 26 comment explains why the short segment matters. The finished quarter mile is the step the city needs before it can go back after the larger grant. State Parks puts it the same way, saying any continuation of Eldon's trail depends on future grants.
It helps to know how big the project could get. A 2024 Rails-to-Trails Conservancy article described an 18-mile corridor section between Versailles and Eldon, which is still undeveloped. The same article described the earlier Eldon plan as a 1.4-mile project funded by the $250,000 grant. The August 2025 vote replaced that plan with the quarter mile under construction now.
The developed state trail is still far from Eldon. Missouri State Parks describes the open Rock Island Trail as 47.5 miles between Pleasant Hill and Windsor. The 144-mile corridor from Windsor to Beaufort, which includes Eldon, is undeveloped and closed to public use. Even the western end is still being built. State Parks scheduled a ribbon cutting for the Ted and Pat Jones Bridge at Pleasant Hill on Oct. 3, 2026. Eldon's quarter mile is a local link meant to join a statewide trail that is still filling in.
Where the route sits, and what's usable today
The 2025 headline named the Eldon Drive-In as one end of the route, and that landmark is mostly memory now. The Cinema Treasures listing for the theater, also known as the Corral Drive-In, shows it closed by May 1983 and since demolished. The trail uses an old place name, which suits a project built on an old railroad.
As of early October 2026, none of the sources reviewed confirms that Eldon's segment is open. The most recent public record is the Aug. 25 report of the finished fence. The Advertiser ran an update on Aug. 14 titled "On post with the Rock Island Trail," and the full story is for subscribers. State Parks still lists the section as "to be built."
Two railroad-era places are open now. Rock Island Park, named for the same line, has a walking trail, adult exercise equipment, a splash pad, restrooms, East and West pavilions, two playgrounds, swing sets and picnic tables. The Eldon Area Chamber of Commerce works out of the newer depot building, which has a depot museum of Rock Island Railroad artifacts. Its listed hours are Monday through Friday, 8 a.m. to 4:30 p.m. An earlier Columbia Missourian report called the restored station the "Eldon Depot Museum & Visitors' Center Trailhead." Back in 2021, the Friends of Rock Island Trail suggested Eldon's city parks could act as trailheads by sharing their existing parking, water and restrooms. Neither source confirms that trailhead parking has been designated, so the city or Chamber are the best places to check before planning a walk.
The next public updates will come in the Public Works reports at aldermen meetings, which the City of Eldon posts on eldonmo.org. That is also where any grant reapplication should first appear. For more on the town around the trail, see our Eldon neighborhood page and Eldon's small-town appeal.